Guernsey Law Reports 2009-10 GLR 142
MINISTER OF THE PUBLIC SERVICES DEPARTMENT v. MILLER AND BAIRD (C.I.) LIMITED
ROYAL COURT (Collas, Deputy Bailiff and Jurats): May 15th, 2009
Companies—compulsory winding up—grounds for winding up—inability to pay debts—presumption that court will grant application unless (a) genuine and serious cross-claim of substance; (b) company not reasonably able to litigate earlier; and (c) exceeds debt claimed by creditor—may then refuse to grant application unless creditor shows exceptional circumstances—exceptional circumstances only if company has ceased trading and other creditors and members not prejudiced by refusal
The States applied for the winding up of the defendant company on the ground that it was unable to pay its debts within the meaning of the Companies (Guernsey) Law 2008, s.406(e).
The company had contracted to carry out major building works to construct a marina at St. Sampson’s Harbour. It failed to fulfil the contract and incurred substantial liabilities to the States, which in December 2008 served a statutory demand on the company for £93,396.87, a sum which then remained unpaid for more than 21 days. It was therefore deemed to be unable to pay its debts within the extended meaning given to the phrase by s.407 of the Companies (Guernsey) Law 2008, and the States applied to wind it up.
The company had, however, raised a number of cross-claims arising out of the performance of the contract. It had encountered a series of unforeseen problems relating to the state of the sea-bed at the building site, which extended the time for completing the work and caused it substantial additional expense. It had made four separate claims between April and July 2005 which the States Engineer, in his capacity as the independent engineer under the contract, rejected at various times between October 2005 and June 2006. The claims were elaborately documented and the replies took some considerable time to prepare. In the end, after further correspondence which did not resolve the disagreements, the company submitted its final account in November 2007 and the Engineer issued his final certificate in February 2008. The company continued to press its claims, however, and it was ultimately agreed that the continuing disputes should be referred to arbitration, as provided for in the contract, which the company did on April 29th, 2009.
2009–10 GLR 143
The court’s discretion
The parties agreed that, even though the company was unable to pay its debts, the court nevertheless had a discretion under s.406(e) whether to grant the application for winding up. Similarly, both parties were in agreement that the court should only consider exercising its discretion not to grant the application if (a) there were a genuine and serious cross-claim of substance; (b) the company had not reasonably been able to litigate the claim; and (c) the cross-claim was of an amount exceeding the debt on which the application for winding up was based. If the company were to satisfy the court that it should exercise its discretion to dismiss the application for winding up, the burden would then fall on the States to show that there were exceptional circumstances which justified the court’s not doing so. If there were no such exceptional circumstances, the final decision to be made would be whether the court should dismiss the application for winding up or merely stay it pending the conclusion of the arbitration.
(a) Genuine and serious cross-claims
The States submitted that there were several periods of delay in the conduct of the negotiations over the cross-claims (commencing in December 2005), during which the company might legitimately have challenged the Engineer’s decisions by taking the disputes to arbitration. That it had not done so supported the view that it did not treat the cross-claims with sufficient seriousness. The decisions of the Engineer were prima facie binding but that did not preclude the possibility that they might be overturned on arbitration and the company should have pursued this possibility more urgently. There was also a further period of unaccountable delay following the Engineer’s issue of his final certificate in February 2008, when the company should have been prepared to act quickly, bearing in mind that its trading activities had either ceased or were winding down.
The company submitted in reply that (a) it was reasonable to delay referring the various disputes to arbitration as it wished to refer all of them at the same time and have them resolved in a single arbitration rather than piecemeal; (b) its commitment to the cross-claims was supported by an indication from independent experts employed by its specialist solicitors that it had “genuine, serious and substantial claims” to advance in the arbitration proceedings, which far exceeded the sum claimed by the States; and (c) the family of the principal director of the company had sufficient confidence in the cross-claims that it had already committed £120,000 to funding them and was willing to commit a further £55,000 to complete the arbitration.
(b) The company’s ability to sue on the cross-claims
The States submitted that, in the light of their submission above, the company had been in a position to litigate its cross-claims had it wished to do so. The company submitted in reply that the delays caused by the complexity of the claims and the course of the negotiations had made it
2009–10 GLR 144
impractical to litigate and it had taken the first opportunity it had had to seek an independent resolution of the disputes (by reference to arbitration).
(c) The cross-claims exceeding the debt
The company submitted that, although the precise amount sought by the cross-claims was uncertain, its counsel indicated that it was in the order of £3.7m. The sum claimed by the States in its statutory demand—£95,396.87—was so small in comparison that, even if the company were not successful in recovering the whole amount it claimed, it was clear that the cross-claims substantially exceeded the statutory demand.
The company therefore submitted that, unless the States could show the existence of exceptional circumstances, the court should exercise its discretion so as not to grant the application for compulsory liquidation.
Exceptional circumstances
It was accepted that sufficient exceptional circumstances could only be shown if the company had ceased trading and its other creditors and members would not be prejudiced if it were not wound up. It had in fact ceased trading in September 2008 and its principal director indicated that considerable prejudice would be caused to its other creditors if it were immediately wound up. The total amount owed to those creditors was £1.33m., with a further £414,500 owed to the States. Apart from plant worth an estimated £20,000, the company’s only substantial asset was the cross-claims against the States and the creditors were therefore dependent for payment upon the success of the cross-claims. Four major creditors indicated as much in writing and expressed their opposition to the winding-up application.
Moreover, the director’s family was committed to making available additional funding to continue to pursue the arbitration process. It also pointed out the conflicts of interest that would arise if liquidators appointed on the application of the States and funded by the States were the persons taking decisions about the conduct of an arbitration in a dispute with the States.
The States warned against attaching weight to statements made by creditors without knowing what information had been given to them or whether they understood the issues involved. They indicated, however, that if the company were wound up, they would neither provide further funding for litigation by the company, save for a nominal sum to enable the liquidators to seek legal advice, nor would they fund the liquidators to pursue the arbitration, leaving them to approach the director’s family or seek finance from other creditors.
Dismissal or stay
The question remained whether, if the winding-up application were not to be pursued, it should be dismissed or stayed. The States submitted that it should be stayed since, if at any time the arbitration were not being
2009–10 GLR 145
progressed quickly enough by the company, the States would be able to reactivate the winding up.
The company submitted in reply that there was no need to stay the application, which should be dismissed. This would follow the English practice in these circumstances, which was desirable unless there were good reason not to do so. Since the company had already initiated the arbitration procedure and was proceeding to find and agree upon an arbitrator, there was no reason to believe that further delay would ensue or that there would be any justification for the States to consider reactivating the winding up.
Held, dismissing the application to wind up the company:
The court’s discretion
(1) Although the company was deemed by the Companies (Guernsey) Law, s.407 to be unable to pay its debts, which was a sufficient ground for winding up, the court had a discretion under s.406(e) whether to grant the application. It would only consider exercising that discretion against granting the application, however, if the company were able to establish (a) there were a genuine and serious cross-claim of substance, which (b) the company had not reasonably been able to litigate, and (c) it exceeded the debt on which the application for winding up was based (para. 9).
(a) Genuine and serious cross-claims: The Jurats accepted that the company’s cross-claims were real, not frivolous and had substance. The delays attributed to both parties (and to the company in particular) were not so long as to suggest that the cross-claims lacked substance but rather indicated the complexity of the issues the parties had to address. They accepted that the financial commitment shown by the family of the company’s principal director showed its confidence in the merits of the cross-claims and, although they believed that the supportive letter from the independent experts could be regarded as self-serving, they did not believe that it could be totally ignored (paras. 27–29).
(b) The company’s ability to sue on the cross-claims: The Jurats concluded that since the admitted delays were not unreasonable, for the reasons given by the company, it had not reasonably been able to sue on the cross-claims before the States had made its application for winding up and had in fact pursued the independent resolution of the disputes (by the reference to arbitration) as soon as it had been able to do so (para. 30).
(c) The cross-claims exceeding the debt: The Jurats were satisfied that although the precise amount sought by the cross-claims was uncertain, it was well in excess of £3m. and therefore—even if the company were not successful in recovering the whole amount it claimed—it was clearly in excess of the States’ unsatisfied statutory demand for £95,396.87 (paras. 31–32).
2009–10 GLR 146
The court was therefore persuaded that, unless the States could show exceptional circumstances, it should exercise its discretion so as not to grant the application for compulsory liquidation (para. 33).
Exceptional circumstances
(2) The States had not satisfied the burden of establishing circumstances exceptional enough to persuade the Jurats that the winding-up application should be allowed to proceed. They were satisfied that if it were to be dismissed, the company would have the financial resources (through the support of the principal director’s family) to pursue the arbitration to completion. Moreover, the directors of the company would be better able to pursue the arbitration proceedings more robustly than liquidators and it was understandable that the director’s family would be more prepared to fund the arbitration if they were in charge of their own case. If, on the other hand, the company were to be wound up, neither the family nor the creditors would be prepared to fund the arbitration proceedings, arbitration would not be pursued and, after the payment of the liquidators’ expenses, little or nothing would be available for the creditors (para. 40; paras. 44–45; para. 47).
Dismissal or stay
(3) The Jurats accepted that it was proper for them to adopt the English practice and dismiss the winding-up application rather than stay it. There was no good reason for the court to exercise its discretion to depart from this practice and instead stay the application. The arbitration procedure was in place, steps were being taken to appoint an arbitrator who, once appointed, would have the conduct of the arbitration. If any further delay were to occur through the fault of the company, the States would of course be able to make a fresh application for winding up and would be able, if they wished to do so, to rely upon the material already produced to the court, with the addition of any up-dating information necessary (paras. 49–52).
Cases cited:
(1) Atlantic & Gen. Inv. Trust Ltd. v. Richbell Information Servs. Inc., [2000] 2 BCLC 778; [2000] BCC 111, considered.
(2) Bayoil S.A., In re, [1999] 1 W.L.R. 147; [1999] 1 All E.R. 374; [1999] 1 Lloyd’s Rep. 211; [1999] 1 BCLC 62; [1998] BCC 988, applied.
(3) L.H.F. Wools Ltd., In re, [1970] Ch. 27; [1969] 3 W.L.R. 100; [1969] 3 All E.R. 882, applied.
Legislation construed:
Companies (Guernsey) Law 2008, s.406(e): The relevant terms of this section are set out at para. 6.
s.407: “For the purposes of section 406(e) . . . a company shall be deemed to be unable to pay its debts if—
(a) a creditor to whom the company owes a sum exceeding £750 which is then due serves on the company . . . at the
2009–10 GLR 147
company’s registered office a written demand for payment, and
(b) the company, for a period of 21 days immediately following the date of service, neglects to pay the sum or to secure payment to the reasonable satisfaction of the creditor . . .”
Miss K.E. Walder for the plaintiff;
J.P. Greenfield for the defendant.
1 COLLAS, DEPUTY BAILIFF:
Introduction
In this judgment we will refer to the plaintiff as “the States,” to Miller & Baird (C.I.) Ltd., the defendant, as “the company,” and to the contract between the parties for major works to create a marina at St. Sampson’s Harbour as “the contract.”
2 In an amended application dated April 7th, 2009 (“the application”), the States applied for an order that the company be compulsorily wound up and for the appointment of two insolvency practitioners from the local firm of Grant Thornton Ltd. as joint liquidators.
3 The application was supported by affidavit evidence. The States relied upon an affidavit sworn by Adrian Robin Lewis, the Chief Officer of the Public Services Department, on March 24th, 2009. The company produced three affidavits: one from Ian Graham, a director of the company, sworn on April 24th, 2009; another from Simon Graham, his son, sworn on the same day; and a third sworn by Advocate Greenfield on May 5th, 2009. We had the benefit of written submissions filed on behalf of each of the parties and of the clear and concise oral arguments of their respective advocates, who we heard on May 6th.
4 At the conclusion of the hearing, the Deputy Bailiff and Jurats retired to consider their decision. The Jurats decided unanimously to dismiss the application and the court reserved its reasons, which are now handed down in this judgment.
5 In this judgment, questions of law and procedure are decided by the Deputy Bailiff; all questions of fact are decided by the Jurats who agree unanimously on all factual conclusions.
The law
6 Section 406(e) of the Companies (Guernsey) Law 2008, provides that—
“A company may be wound up by the Court if—
. . .
2009–10 GLR 148
(e) the company is unable to pay its debts within the meaning given in section 407 . . .” [Emphasis supplied.]
7 The parties agreed that the requirements of s.407 had been satisfied in that the States served a statutory demand on the company on December 22nd, 2008 in the sum of £95,396.87, that amount had not been paid and it remained outstanding at the date of the hearing. The amount claimed is the total of two separate sums; the first is the amount due under a judgment dated November 14th, 2008 in respect of occupation fees payable in lieu of rent for land occupied by the company at St Andrew’s Reservoir, together with interest thereon and costs; and the second is the amount due to the States in respect of recoverable costs awarded against the company by the Court of Appeal on December 15th, 2005.
8 The company is therefore deemed to be unable to pay its debts under the provisions of s.407 of the Companies Law and the court has a discretion whether or not to grant the application.
9 Neither counsel was able to refer the court to any decision of the Guernsey courts as to the circumstances in which such discretion is to be exercised. Both counsel agreed that the decision of the English Court of Appeal in In re Bayoil S.A. (2) is a persuasive authority establishing that the court should only consider exercising its discretion so as not to grant the application if—
(a) there is a genuine and serious cross-claim or, as Nourse, L.J. expressed it ([1999] 1 W.L.R. at 155), a claim of substance;
(b) the company must have been unable to litigate the claim or, to quote the headnote to In re L.H.F. Wools Ltd. (3) in the Law Reports ([1970] Ch. at 28) there must be a claim which the company “had not reasonably been able to litigate”; and
(c) the cross-claim is in an amount exceeding the amount of the States’ debt.
10 Counsel agreed that in relation to these matters, the burden is on the company to satisfy the court that it should not exercise its discretion so as to grant the application. If the court so decides, counsel agreed that the court has a residual discretion not to dismiss the application exercisable only in exceptional or rare circumstances, namely, if the company has ceased trading and there would be no prejudice suffered by other creditors and members of the company if it is wound up. In relation to that issue, the parties agreed that the burden shifted to the States.
11 The Deputy Bailiff directed the Jurats that the standard of proof is the normal civil standard of the balance of probabilities and that to establish something on the balance of probabilities means to prove that something is more likely so than not so.
2009–10 GLR 149
Genuine and serious cross-claim?
12 Advocate Greenfield referred to an extract from Practical Law Company—Responding to a Winding-up Petition: A Guide For Companies, which, in the extract produced to the court states, under the heading “Disputed Debt on Substantial Grounds”:
“The court will not make a winding-up order against a company where the petition debt is genuinely disputed by the company on ‘substantial grounds’. In this context ‘substantial’ means that the dispute must be ‘real as opposed to frivolous’ (Commissioners of Customs & Excise v. Arena Corporation Ltd., [2004] EWCA Civ 371). A ‘mere honest belief that payment is not due’ will not suffice (Re a Company (No 0010656 of 1990), [1991] BCLC 464). There must be sufficient evidence to persuade a court that objectively there is a genuine dispute as to the company’s liability to pay the debt. Once it is established that there are substantial grounds for disputing the claim, ‘the court should not go on to consider the prospects of success of either party to the dispute’ (Abbey National plc v. JSF Finance & Currency Exchange Co. Ltd., [2006] EWCA Civ 328).”
Factual background
13 The cross-claim arises out of the contract whereby the company was employed to carry out major works in order to create a marina in St. Sampson’s harbour. The works commenced on June 9th, 2003. The company claims that it encountered a number of problems thereafter, including unforeseen ground conditions beneath sea level, which led to an extension in time for the completion of the works and as result the company incurred additional costs and expenses which it seeks to recover from the States.
14 Each party produced to the court a chronology of relevant events. We prefer to refer to that produced by Advocate Greenfield in the exhibit to his affidavit as it is more comprehensive than that produced on behalf of the States.
15 The company has submitted four claims for payment of additional costs. The first was submitted on April 8th, 2005 for “the additional costs incurred as a consequence of unforeseen geological conditions encountered during the construction of the South Cill.” The other three were submitted on July 25th, 2005 and were in respect of “drilling and socketing for guide piles—additional works,” “additional direct costs incurred as a consequence of ordered variations in the method and timing of sediment excavation, transport and other excavation work,” and “additional costs arising due to disruption of the works and prolongation of the contract period.”
2009–10 GLR 150
16 The claims were all submitted to the States Engineer in his capacity as the independent engineer appointed by the parties under the terms of the contract. The court is unable to assess the merits or validity of the claims but it notes that each claim is detailed, documented and lengthy. The States Engineer responded to the first submission on October 5th, 2005, to the third submission on February 21st, 2006, to the second submission on March 20th, 2006 and to the fourth submission on June 15th, 2006. The latter was nearly 11 months after the claim was submitted.
17 The company submitted a rebuttal of the Engineer’s responses on January 9th, 2007, to which the Engineer replied on October 12th, 2007. It submitted its final account on November 16th, 2007 and the Engineer issued a final certificate on February 16th, 2008.
18 Nothing further appears to have happened until November 6th, 2008 when Bevan Brittan wrote to the Engineer on behalf of the company requesting a decision on a dispute under cl. 66 of the contract. Bevan Brittan, we were told, is a firm of specialist solicitors instructed by the company to represent it in relation to matters arising under the terms of the contract. A number of letters have been exchanged between Bevan Brittan and the States Engineer since November 6th and a copy of the correspondence is exhibited. Bevan Brittan is challenging the States Engineer’s decisions regarding the physical conditions encountered by the company particularly in the area of the South Cill. The States Engineer has stood by his earlier decisions and the correspondence has not satisfied the company’s concerns.
19 In a letter dated February 27th, 2009, the Chief Officer of the Public Services Department of the States agreed that under the contract the company had until May 1st, 2009 to refer the disputes identified in the correspondence to arbitration. That agreement was expressed to be subject to any other remedies the States might have, including the winding up of the company. On April 29th, 2009, the company submitted a formal notice to refer a dispute to arbitration.
20 Advocate Greenfield referred the court to a letter dated 5th May 2009 from Bevan Brittan in which Bevan Brittan advised that it continues to act for the company in its disputes and in the matter of the reference to arbitration by the company of its dispute over the Engineer’s decisions. It confirms that the company’s claims have been supported by independent expert reports of a Mr. Hislam and of a firm called Greyhawk Global. The letter concludes:
“Based on the views of the independent experts, Mr. Hislam and Greyhawk Global, Miller & Baird have genuine, serious and substantial claims in the arbitration proceedings against the States which should far exceed the amount of £95,000 claimed by the States.”
2009–10 GLR 151
Is there a genuine and serious cross-claim?
21 Advocate Walder submits that the Engineer’s decisions are binding unless and until they are overturned. The court recognizes that the Engineer has reached his decisions in an independent capacity and not as an employee of the States of Guernsey. However, the independent status of the Engineer does not preclude the possibility of his decisions being challenged before an arbitrator. In the opinion of the court, neither the fact that the decisions are binding until overturned nor the fact of the Engineer’s independence is a determining factor in deciding whether there is a genuine and serious cross-claim.
22 Advocate Walder also argued in her written submissions, that “the chronology points to a plethora of wasted opportunities” to arbitrate, which she submitted should be taken into account in assessing the seriousness of the cross-claim. In her oral submissions, Advocate Walder identified two periods of delay.
23 The first period of delay was following the judgment of the Court of Appeal, handed down on December 15th, 2005, whereby the Court of Appeal allowed an appeal from a decision of the Royal Court and ordered that proceedings instituted by the company be stayed, pursuant to s.4 of the Arbitration (Guernsey) Laws 1982 and 1986. Delay occurred because the company failed to take steps to refer the matter to arbitration until it commenced proceedings by issuing the notice dated April 29th, 2009.
24 The company explained that it was reasonable to delay referring disputes to arbitration, as it wanted to wait until it was able to submit a reference in respect of all disputes so as not to have a number of separate arbitrations. The Jurats accept that explanation.
25 The second period of delay relied upon by the States is from February 16th, 2008, when the Engineer issued a final certificate, until November 6th, 2008 when the company filed its first request for a decision from the Engineer under cl. 66 of the contract. She argued that the company should have been prepared in advance of receiving the final certificate and should have acted more quickly, especially as its trading activities had either ceased or were winding down.
26 The Jurats have carefully considered the periods of alleged delay. They have done so by reference to the chronology as a whole and to the periods of time taken by the company and the States Engineer to discharge their respective responsibilities and to respond to requests. No explanations have been given for what appear to be some delays on the part of the States Engineer at various times. The Jurats express no criticism of the manner in which the States Engineer has conducted himself and they have paid no attention to the apparent criticism by Hancox, Lieut. Bailiff, in para. 73 of his judgment in the earlier court proceedings.
2009–10 GLR 152
27 In the view of the Jurats, the length of time that has been taken to progress aspects of the matter is indicative of the complexity of the issues involved. The Jurats believe that any delays that have occurred have not been of such great length that they could conclude the delays are indicative of a lack of substance in the company’s cross-claims.
28 The Jurats are in no position to discuss the merits of the cross-claim and it is not their function to attempt to pre-judge the outcome of the arbitration. So, the Jurats cannot examine the cross-claims in detail, but can only observe that a very significant amount of work has been done to support the company’s claims; the requests for payment are detailed at some length and they are supported by the reports of independent experts who have, apparently, relevant expertise. They take note of the fact that Mr. Simon Graham has sufficient confidence in the merits of the cross-claim to have supported it to the tune of £120,000 to date and he is willing to commit a possible further £55,000 to see the arbitration to a conclusion. In that respect, the matter bears a little similarity to the decision of His Honour Judge Weeks, Q.C. (sitting as a High Court Judge) in Atlantic & Gen. Inv. Trust Ltd. v. Richbell Information Servs. Inc. (1), although in that case the cross-claim was being funded by outside investors and in the present case it may be that Mr. Simon Graham is motivated by family ties to support his father, as Advocate Walder suggested. However, the Jurats do not believe that Mr. Simon Graham would be so supportive if he did not have confidence in the cross-claim. Bevan Brittan, the specialist solicitors instructed by the company, believes that, based on the views of the experts, the company has genuine, serious and substantial claims in the arbitration proceedings. The Deputy Bailiff cautioned the Jurats to take care in the weight to be attached to the letter which was not put forward as sworn evidence and which, as Advocate Walder suggested, could be considered to be self-serving. The Jurats accept that the letter must be treated with some scepticism, but nevertheless they consider that it is supportive and is not to be totally ignored.
29 Taking all the relevant evidence into account, the Jurats conclude that the claim is real, it is not frivolous and it appears to be genuine and serious in the sense of having substance.
Has the company been unable to litigate the matter?
30 As we have said, the Jurats have considered the chronology and have concluded that the delays are not unreasonable for the reasons given above. It follows from that conclusion that the Jurats are satisfied that the company has been unable to litigate the cross-claim, or that it has not reasonably been able to litigate the cross-claim (if that is the relevant test, as is suggested in the headnote to In re L.H.F. Wools Ltd. (3) ([1970] Ch. at 28)).
2009–10 GLR 153
Does the amount of the cross-claim exceed the amount of the States’ debt?
31 The precise amount of the cross-claim is not clear to the Jurats. When Advocate Greenfield was asked the amount, he referred to the final account submitted by the company which claimed a total balance of £3,761,544.85. Advocate Greenfield said there would be some “toing and froing” around that figure.
32 The notice to refer to arbitration identifies a number of disputes and quantifies each one. The parties did not add up the individual items and the Jurats have not done so because some items might contain an element of duplication but they note that many of the items are substantial and they appear to add to a total well in excess of £3m. The company may have pitched its claim in the highest amount possible and hence would not be expected to recover the total amount it is seeking. However, the sum claimed by the States in its statutory demand, £95,396.87, is so small in comparison with the amount the company is claiming that the Jurats are satisfied that the amount of the cross-claim exceeds the States’ debt, even after allowing for the inevitability that the company will not be successful in the full amount of its cross-claim.
33 The court is therefore persuaded that it should consider exercising its discretion so as not to grant the application for compulsory liquidation, unless the States can show exceptional circumstances not to dismiss the application.
Are there exceptional circumstances?
34 The legal test, counsel agreed, is whether the company has ceased trading and there would be no prejudice suffered by other creditors and members of the company if it is wound up.
35 It is common ground that the company ceased trading in September 2008, so the first limb of the legal test is not in dispute. The second limb requires the court to consider whether there would be no prejudice suffered by the other creditors and members of the company if it is wound up. Mr. Ian Graham produced a list of creditors showing that the total amount owed to creditors other than the States is £1,333,000 including preferential creditors totalling £58,000 (excluding rent owed to the States), trade creditors of £308,000, directors’ loans of £500,000, a loan to Barclays of £510,000 and £15,000 owed to claims advisers. £414,500 is owed to the States. So the total amount owed to creditors is £1,805,500.
36 The cross-claim against the States is the only asset of any substantial value; the other assets are items of plant estimated to be worth £20,000. The creditors are therefore looking to the success of the cross-claim, if they are to receive payment.
2009–10 GLR 154
37 The company produced letters from four creditors, namely Ravestein BV, Mr. Phillip Dunne, BDO Novus Ltd. and Marine & General Engineers Ltd., indicating their opposition to the States’ application for compulsory liquidation and confirming that they were hoping for a successful outcome to the cross-claim in order to recover some or all of the debts owed to them.
38 Advocate Walder advised the court against attaching weight to these letters when it did not know what information had been provided to the creditors and it was possible they might not fully understand the issues involved.
39 In the view of the Jurats, the information contained within the letters demonstrates that the people who wrote them do have sufficient understanding of the consequences of compulsory liquidation. In particular, BDO Novus Ltd. said that as well as being a creditor, they were approached by the States with a view to acting as liquidator of the company.
40 Mr. Simon Graham indicated in his affidavit that he had been advised that if the arbitration proceeds, the total cost will exceed £175,000. He has already provided and raised funds for the company to date in the region of £120,000 and said: “I am prepared to continue to be actively involved in ensuring the company has the funds to continue whilst at the same time attempting to minimize its costs in so doing.” His evidence was not challenged in cross-examination. The Jurats are therefore satisfied that if the winding-up application is dismissed, the company will have the financial resources to pursue the arbitration to conclusion.
41 If the company is wound up, the evidence of the States was that it would not provide the funds to pursue any action against the States of Guernsey, but it will provide a maximum of £5,000 to the liquidators to enable them to seek guidance on matters arising in relation to the liquidation.
42 No evidence was produced to show what advice could be obtained for £5,000 and whether that would be sufficient to investigate fully the merits of the cross-claim. One of the proposed liquidators, who was present in court, appeared to cast doubt on whether he had under-estimated the complexity of the issues involved. Even if the sum proposed were sufficient, if the liquidators were to conclude that there was merit in the arbitration proceedings, the States would be requiring them to approach either the Graham family to fund the arbitration, or to seek funds from one or more of the creditors to enable it to do so.
43 There was no evidence as to whether either the Graham family or any creditor would be willing to provide the liquidators with such funds. Even if they were prepared to do so, Advocate Greenfield pointed out the
2009–10 GLR 155
difficulties that would arise if liquidators appointed on the application of the States and funded by the States were the persons taking decisions about the conduct of an arbitration in a dispute with the States.
44 In the view of the Jurats, the director (or directors if there are more than one) of the company will be able to pursue the arbitration proceedings more robustly than the liquidators. It would be understandable that the Graham family might be prepared to fund the arbitration provided the director or directors of the company is or are in control of the company’s case but would not be prepared to do so if the liquidators were in control.
45 If the company is placed in liquidation and neither the Graham family nor the creditors is prepared to fund arbitration proceedings, the arbitration will not be pursued and after payment of the liquidators’ expenses there will be few or no funds available for the preferred creditors and nothing for the non-preferred creditors.
46 Advocate Walder argues that the plant belonging to the company is still located on the States-owned land at St. Andrew’s Reservoir in respect of which the arrears of rent are claimed. That plant could hamper proposals for the redevelopment of St. Andrew’s Reservoir if it is not removed. The liquidators would be in a position to remove the plant and/or to sell it. In the view of the court, the continued presence of the plant on the land does not amount to serious prejudice if the company is not placed in liquidation. The plant has been arrested by H.M. Sheriff at the instance of the States and appropriate steps could be taken, through the offices of H.M. Sheriff, to have the items removed and/or sold if appropriate.
47 In conclusion, the Jurats are not persuaded that exceptional circumstances have been established by the States to persuade them that the winding-up application should be allowed to proceed.
Dismissal or stay?
48 The final issue considered by the Jurats is whether to dismiss the application for winding up or to stay the application pending the conclusion of the arbitration. The advantage of a stay would be that if at any time the arbitration proceedings are not being progressed expeditiously by the company, the States could apply to reactivate the application for a winding up.
49 The Deputy Bailiff directed the Jurats that in the light of the English authorities, the modern practice is to dismiss, rather than stay, such a petition (see, for example, the judgment of Nourse, L.J. in Bayoil (2) ([1999] 1 W.L.R. at 151). However, the court has discretion to stay the application if it is persuaded that there are good reasons for departing from the normal practice.
2009–10 GLR 156
50 The Jurats are not persuaded that there is any need to stay the application. The company has now initiated the arbitration procedures. There is no reason to believe that the company will drag its heels in the appointment of an arbitrator. Once the arbitrator has been appointed, he will have the conduct of the arbitration proceedings.
51 If those proceedings are delayed, or delayed to an unreasonable extent, at the instance of the company, it will be open to the States to bring a fresh application for winding up in support of which the States could rely upon the material already produced to the court if they wished to do so and then would only incur the additional expenditure of updating that information to explain what had happened in the conduct of the arbitration proceedings.
52 So, the court can see no reason to depart from the modern practice of dismissing, rather than staying, the application.
Conclusion
53 Accordingly, the Jurats unanimously decided to dismiss the application. The Deputy Bailiff will sit alone to hear any application for costs; he points out that costs normally follow the event, although Advocate Greenfield has indicated there may be an argument as to whether costs should be awarded on a basis other than the normal recoverable costs basis and Advocate Walder reserved the States’ position until it had seen the reasons for the Jurats’ decision.
Application dismissed.
2010
Law Report
None
Guernsey Law Reports 2009-10 GLR 142